May ’18 cont’d (again!) – Investigation continues

The Carolina Theatre team is still on the case! Groundwater monitoring installation is in progress. The well was installed to determine the depth of the groundwater and to test water samples for contaminants that are common to the Uptown area.

Groundwater was found at approximately 35 feet below existing grade. This is great news for the project as the lowest occupied level of the new space will be only 12 feet below existing grade. It is unlikely that groundwater will have any impact on the construction process.